| Specifications
of Refinery |
{Capacity
5 tonnes per day i.e. 4 batches of 1250 kg. each }
(1) All the main vessels i.e. two
neutralizers, one bleacher and one deodourizer are properly arranged on
the first floor of the steel structure. So all these vessels are hanging
on the steel strucutre. Just below the two neutralizers, two soap pans are
resting on the ground floor in which soap stock is collected. There is a
steam pipe arrangement in the soap pans also.
(2) Steel structure has size of 14ft.
x 14ft. (i.e. 4.25mtr. x 4.25mtr). First floor is 9ft. above the ground
level. There are 8 coloumns of double chanel which supports the entire
steel structure. It has proper staircase and railing on all the sides of
steel structure at the first floor and also on staircase. Two filter
presses are also accomodated on the first floor of the steel structure.
(3) Two oil tanks i.e. raw oil tank
and bleached oil tank are accomodated under the strucutre on the ground
floor. Then cooler, thermic fluid boiler, two steam generators, vacuum
pump, water pumps, oil pumps and refined oil tank are arranged on the
ground floor around the steel structure i.e. outside the square of 14ft. x
14ft. of the steel structure. So total space occupied is about 30ft. ×
30ft. (9mtr. x 9mtr.)
(4) 40ft. tower is erected just near
the deodourizer and its complete structure is supported from the ground
floor and also it is attached with the refinery structure. Berometric
condenser is arranged at 40ft. height to create proper vacuum.
(5) All types of piplines are
interconnected as per the requirement of the refinery i.e. oil pipelines
(yellow colour), vacuum pipelines (blue colour), steam pipelines (black
colour), water pipelines (white colour), thermic fluid pipelines (red
colour). At all appropriate places, proper valves are provided in the
pipelines.
(6) Neutralizer is provided with
thermic fluid coil for heating the oil.
(7) Bleacher is provided with double
pipe coil. One is for thermic fluid and another is for cooling water.
(8) Deodourizer is provided with
double pipe coil i.e. in both the coils, thermic fluid is circulated.
Steam is ejected from the stainless nozzles provided on the steam pipe
cross supported at the bottom.
(9) Cooler is provided with double
pipe coil. Both for cooling water.
(10) In every vessel temperature
guage is provided. Vacuum guage is provided on deodourizer, bleacher and
cooler.
(11) Neutralizer is open on the top
having conical bottom.